What Must Happen Before Demolition Starts? OSHA's Preparatory Operations Rule, 29 CFR 1926.850

Under OSHA's construction rule 29 CFR 1926.850, a competent person must make an engineering survey of a structure before employees start demolition, and the employer must have written evidence of it. Service lines must be shut off, capped or otherwise controlled outside the building line, involved utility companies notified in advance, and it must be determined whether hazardous substances were used in pipes, tanks or other equipment; where their presence is apparent or suspected, testing and purging must be done and the hazard eliminated before demolition starts.

OSHA construction safetyExplainerPublished

Fact-checked against official sources · Last checked

Card reading OSHA construction safety, Explainer: Before demolition starts: the survey, utilities and hazards in 29 CFR 1926.850. eCFR, Nov 17, 2026
Image: goraedu · Own work

OSHA's construction standards put the first steps of a demolition job in 29 CFR 1926.850, "Preparatory operations," the opening section of Subpart T (Demolition). This explainer answers one practical question from that section: what does it require before and during demolition? Paragraphs (a), (c) and (e) are tied to the start of work; the others set conditions without a start-of-work deadline or apply while work is under way. It reads the section as it stands in the eCFR and does not describe a rule change.

An engineering survey by a competent person

Paragraph (a) states: "Prior to permitting employees to start demolition operations, an engineering survey shall be made, by a competent person, of the structure to determine the condition of the framing, floors, and walls, and possibility of unplanned collapse of any portion of the structure."

The survey reaches beyond the building being demolished: "Any adjacent structure where employees may be exposed shall also be similarly checked." And it must be documented: "The employer shall have in writing evidence that such a survey has been performed."

If the structure is already damaged, paragraph (b) adds: "When employees are required to work within a structure to be demolished which has been damaged by fire, flood, explosion, or other cause, the walls or floor shall be shored or braced."

Utilities shut off or controlled

Paragraph (c) states: "All electric, gas, water, steam, sewer, and other service lines shall be shut off, capped, or otherwise controlled, outside the building line before demolition work is started. In each case, any utility company which is involved shall be notified in advance."

When a service has to stay on, paragraph (d) applies: "If it is necessary to maintain any power, water or other utilities during demolition, such lines shall be temporarily relocated, as necessary, and protected."

Hazardous substances found and removed

Paragraph (e) states: "It shall also be determined if any type of hazardous chemicals, gases, explosives, flammable materials, or similarly dangerous substances have been used in any pipes, tanks, or other equipment on the property. When the presence of any such substances is apparent or suspected, testing and purging shall be performed and the hazard eliminated before demolition is started."

Glass, openings and floor holes

  • Glass. "Where a hazard exists from fragmentation of glass, such hazards shall be removed" (paragraph (f)).
  • Wall openings. "Where a hazard exists to employees falling through wall openings, the opening shall be protected to a height of approximately 42 inches" (paragraph (g)).
  • Floor openings not used as material drops. They "shall be covered over with material substantial enough to support the weight of any load which may be imposed. Such material shall be properly secured to prevent its accidental movement" (paragraph (i)).

Dropping debris through floor holes without a chute

Paragraph (h) states: "When debris is dropped through holes in the floor without the use of chutes, the area onto which the material is dropped shall be completely enclosed with barricades not less than 42 inches high and not less than 6 feet back from the projected edge of the opening above." It adds: "Signs, warning of the hazard of falling materials, shall be posted at each level. Removal shall not be permitted in this lower area until debris handling ceases above."

The order of work: top down

Paragraph (j) sets the sequence. Apart from "the cutting of holes in floors for chutes, holes through which to drop materials, preparation of storage space, and similar necessary preparatory work, the demolition of exterior walls and floor construction shall begin at the top of the structure and proceed downward." It continues: "Each story of exterior wall and floor construction shall be removed and dropped into the storage space before commencing the removal of exterior walls and floors in the story next below."

Protected entrances

Paragraph (k) states: "Employee entrances to multi-story structures being demolished shall be completely protected by sidewalk sheds or canopies, or both, providing protection from the face of the building for a minimum of 8 feet." The canopies "shall be at least 2 feet wider than the building entrances or openings (1 foot wider on each side thereof), and shall be capable of sustaining a load of 150 pounds per square foot."

Access into the building

The next section, 29 CFR 1926.851, limits how workers get in and around: "Only those stairways, passageways, and ladders, designated as means of access to the structure of a building, shall be used. Other access ways shall be entirely closed at all times" (paragraph (a)). In a multistory building, a stairwell in use must be "properly illuminated by either natural or artificial means, and completely and substantially covered over at a point not less than two floors below the floor on which work is being performed" (paragraph (c)).

Study with goraedu

Our OSHA construction safety hub collects our construction study guides and practice tests. The general safety study guide covers the general rules of Subpart C, and our earlier explainer on debris chutes and dropping waste under 1926.252 covers the general rule for disposing of waste materials. The demolition subpart itself is not part of our study guides.

Sources

Found an error? Email [email protected]. We review reports within 7 days and log fixes on the corrections page.